Project Archive

Built Proof: Projects

Case studies presented like job tickets — bold codes, square footage, timelines, and budget variance in high-contrast data strips. Filter by use type to surface relevant build‑outs.

OFC-742

18,200 SF headquarters refresh for an energy trading firm in Uptown Houston. Live-floor work; zero downtime.

Office Occupied

  • SF 18,200
  • Weeks 14
  • Budget −1.8%
  • COs 2

View case

RTL-311

4,600 SF high-contrast build-out for an apparel flagship at a Galleria-adjacent retail bay.

Retail Shell

  • SF 4,600
  • Weeks 9
  • Budget +0.0%
  • COs 1

View case

MED-228

12,400 SF outpatient clinic conversion with 14 exam rooms, two procedure suites, and medical gas integration.

Medical Conversion

  • SF 12,400
  • Weeks 16
  • Budget −1.2%
  • COs 0

View case

OFC-675

9,100 SF legal workplace with case-rooms, sound attenuation, and custom millwork library wall.

Office TI

  • SF 9,100
  • Weeks 10
  • Budget −0.6%
  • COs 1

View case

RTL-404

2,800 SF quick-turn café with back-of-house rework, grease intercept tie-in, and storefront upgrade.

Retail Fast Turn

  • SF 2,800
  • Weeks 6
  • Budget −0.3%
  • COs 0

View case

MED-193

5,700 SF dental suite expansion with nitrous manifold, vacuum pump redundancy, and acoustical privacy.

Medical Expansion

  • SF 5,700
  • Weeks 8
  • Budget −2.1%
  • COs 0

View case

Case File

OFC-742 — Energy HQ Refresh

Open benching with ad‑hoc cabling. Legacy lighting grid. Carpet tiles at end-of-life.

Re-zoned power/data, suspended acoustic baffles, task-tuned LED, and rubber-backed aisle runners.

Blueprint overlays guided phased demolition to maintain egress and trading uptime. Night shifts removed the heaviest noise and dust operations.

  • Code OFC-742
  • Type Office TI
  • SF 18,200
  • Timeline 14 weeks
  • Budget Var. −1.8%
  • COs 2 (owner-directed finishes)

Coordinated permitting with City of Houston; expedited electrical plan review to sync with lighting package lead times. Staggered demo, shielding, and negative air ensured live trading desks remained operational.

Scope included new server room containment, supplemental CRAC tie-in, DIRTT partitions for huddle rooms, custom millwork coffee points, and over-aisle power bussing with quick-disconnect whips for future moves.

QC ensured acoustic targets (≤40 dBA in focus rooms) and light levels (350–400 lux at workplane). Commissioned with punchlist compressed into a single weekend window.

They hit a weekend cutover with zero desk relocations and turned our ‘wish list’ into clean, inspectable details.
Director of Facilities, Energy Trading Client

Ask about occupied-floor phasing Back to index

Case File

RTL-311 — Apparel Flagship

Shell space with uneven slab, rough storefront mullions, and undersized RTUs.

Level slab, polished overlay, powder-coated mullions, and a clean lighting datum that drives the merchandising line.

Grit pass: slab correction mapped like a topographic survey; we pre-cut control joints to align under gondolas.

  • Code RTL-311
  • Type Retail TI
  • SF 4,600
  • Timeline 9 weeks
  • Budget Var. +0.0%
  • COs 1 (owner signage)

Subcontractor stack sequenced for brand deadlines: fast-cure slab work, then MEP rough, then a four-day finish blast. We overlaid the lighting grid with fixture delivery to avoid rehangs.

Permitting coordinated with landlord criteria and City of Houston for storefront alteration. Final clean delivered 36 hours pre-visual merchandising to allow fixture staging.

See retail fast-turn method Back to index

Case File

MED-228 — Outpatient Clinic

Former office floor with low-density power, standard return-air path, no medical gas provisions.

14 exam rooms, two procedure suites, nurse station, sterilization, vacuum and O2 manifolds with alarm panel.

We modeled duct acoustics and door undercut tolerances to preserve privacy across the exam block.

  • Code MED-228
  • Type Medical Conversion
  • SF 12,400
  • Timeline 16 weeks
  • Budget Var. −1.2%
  • COs 0

Coordinated plan review with City of Houston and life-safety compliance; integrated medical vacuum, oxygen, and WAGD with zone valves and emergency shutoffs. All brazing inspected and logged with pressure decay tests.

QC covered cleanability (coved base transitions), 20 ft-candle minimum in procedure suites, and HIPAA-aligned acoustical privacy. Commissioning included alarm annunciation tests and nurse call verification.

Review medical QC checklist Back to index

Delivery Metrics

Performance at a Glance

96.4%
On-time

Projects hit promised turn dates across the last 24 months.

-1.1%
Budget Var.

Average variance against signed GMP or stipulated sum.

4.8
QC Score

Closeout average out of 5 from third-party punch audits.

See how we schedule and track

FAQ

Project Questions

How do your filters work without downtime to users?

Use the tags above to jump to representative case studies by sector. For a deeper cut to your spec (building, city quadrant, MEP needs), email contact@beardsleycrestpoint.com and we’ll send a filtered package with drawings and sub lists.

What’s included in your case documentation?

Permit set, approved finish schedule, sub roster, two-week look-aheads, inspection log, commissioning checklist, and final lien releases. We redact client identifiers on request.

Can you execute in occupied spaces?

Yes. We plan phased barriers, negative air, and off-hours noise windows. See OFC-742 for an occupied-floor example with zero operational downtime.

Do you self-perform trades?

No. We manage a vetted roster of subcontractors and keep competitive tension through scope packages and schedule hold-points. QC is handled by our superintendent and a rotating third-party punch lead.

Next Step

Bring us your plan set

Whether it’s a 3,000 SF fast-turn retail bay or a 20,000 SF medical conversion, we’ll return a schedule, a permit path, and a clean budget in writing.

Start a project

Email drawings

BEARDSLEY CRESTPOINT LLC • 4545 POST OAK PLACE DR STE 225, HOUSTON, 77027-3140, TX, USA